Complexity: 1 Single straightforward task
Effort: 1 < 2 hours
Uncertainty: 1 Clear requirements & solution
1 is the minimum value used (uncertainty).
1 is the mean value with a standard deviation of 0.
1 is the closest point value.
1 is the closest point value over the mean.
1 is the maximum value (complexity).
Points Complexity Effort Uncertainty
1 Single straightforward task < 2 hours Clear requirements & solution
2 Simple task with known solution 2-4 hours Minor clarifications needed
3 Multiple simple tasks 4-8 hours Some unknowns exist
5 Multiple interconnected tasks 1-2 days Several unknowns
8 Complex problem, clear approach 2-3 days Significant unknowns
13 Complex problem, multiple approaches 3-5 days Many dependencies
21 System-wide changes needed 1-2 weeks Technical feasibility unclear
34 Multiple system interactions 2-3 weeks High risk areas identified
55 Architectural changes required 3-4 weeks Major unknown dependencies
89 Too complex to estimate > 1 month Cannot estimate confidently